Petrobras' P-79 FPSO Completes First Oil Offloading at Búzios Field

Petrobras' P-79 FPSO Completes First Oil Offloading at Búzios Field.jpg

Petrobras' P-79 floating production, storage and offloading (FPSO) unit has completed its first oil offloading after beginning operations at the Búzios field offshore Brazil, according to shipbuilder Hanwha Ocean.

Hanwha Ocean, which carried out the engineering, procurement and construction of the vessel's hull and topsides, said the FPSO departed its Geoje shipyard in South Korea in November 2025 and arrived in Brazil in February.

The vessel produced first oil on May 1 and completed its first oil offloading on May 30.

The startup follows Petrobras' announcement in May that the P-79 had begun production three months ahead of the schedule outlined in its 2026-2030 business plan and five months ahead of the timeline in its previous plan.

The P-79 has a production capacity of 180,000 barrels of oil per day and gas compression capacity of 7.2 million cubic metres per day. The vessel is expected to increase the installed production capacity of the Búzios field to about 1.33 million barrels per day.

Petrobras said the project will also enable gas exports to the mainland through an interconnection with the Rota 3 gas pipeline.

The FPSO forms part of the Búzios 8 development project, which includes 14 wells comprising eight producers and six injectors.

Located about 180 km off the coast of Rio de Janeiro in the Santos Basin, Búzios is Brazil's largest field by reserves and one of the world's largest deepwater oil developments. The P-79 is the eighth FPSO operating at the field, where production exceeded 1 million barrels per day in 2025.

The Búzios consortium comprises Petrobras as operator, Chinese partners CNOOC and CNODC, and PPSA, which manages the production-sharing contracts.


Floating Production Week delivers unrivaled overview, insight and analysis to the Offshore Floating Production Systems and Technology market

Floating Liquefaction and Regasification Report And Online Database

  • Annual reports -- Our new 150-page report is the first professional effort to systematically look at the universe of FLNG and FSRU projects in the planning stage – and categorize the likelihood of each making the development investment hurdle.
  • Online database -- The online database is updated every day – with information direct from primary sources. The database is fully searchable. Customized charts and spreadsheets can be directly produced from the database.
  • Customer support -- We are available to assist with technical questions about information in the database and reports -- and assist with any questions about using the database search tools.

Here's what you get!

Request Free Trial