FPSO for Greater Tortue Gas Project Due in Senegal by end-2022

credit-image-128292.jpg

BP's floating, production, storage, and offloading vessel (FPSO) for the Greater Tortue Ahmeyim gas project offshore West Africa is expected in Senegal waters for commissioning and testing by the end of 2022, a company executive said on Friday.

The FPSO for the project, which straddles Senegal and Mauritania, is being built in China by France's Technip Energies.

Massaer Cisse, BP's vice-president, and Senegal country director told an oil conference in Dakar that the FPSO will be in Senegalese waters by the end of 2022.

The FPSO is 83% complete and will be connected to the field for testing in early 2023 before being delivered to the operator in mid-June 2023, Franck Pliya, Senegal country director for Technip Energies, told the conference.

Project operator BP bought the FPSO from project partner Kosmos in a deal concluded in August, Kosmos said at the time.

First gas from the project is expected by the end of 2023. 

(Reporting by Bate Felix; editing by Jason Neely)



Floating Production Week delivers unrivaled overview, insight and analysis to the Offshore Floating Production Systems and Technology market

Floating Liquefaction and Regasification Report And Online Database

  • Annual reports -- Our new 150-page report is the first professional effort to systematically look at the universe of FLNG and FSRU projects in the planning stage – and categorize the likelihood of each making the development investment hurdle.
  • Online database -- The online database is updated every day – with information direct from primary sources. The database is fully searchable. Customized charts and spreadsheets can be directly produced from the database.
  • Customer support -- We are available to assist with technical questions about information in the database and reports -- and assist with any questions about using the database search tools.

Here's what you get!

Request Free Trial