BW Offshore's FPSO Marks Key Performance Milestone on Barossa LNG Project

BW Offshore's FPSO Marks Key Performance Milestone on Barossa LNG Project.jpg

BW Offshore has completed the Interim Performance Test (IPT) for the BW Opal floating production, storage and offloading (FPSO) vessel, marking a significant commissioning milestone for the Santos-operated Barossa LNG project offshore northern Australia.

The successful completion of the IPT confirms that the FPSO's key production, processing and utility systems are operating in an integrated manner and are capable of delivering stable performance under production conditions.

The milestone follows the achievement of first gas in September 2025, which marked the transition of the BW Opal from the project phase into operations and initiated 60% of the contractual day rate under the vessel's charter agreement.

Under the contract structure, completion of the IPT increases the payable day rate to 85%, while the next milestone, Practical Completion, will trigger the full contractual day rate and mark the start of the 15-year firm charter period.

Following the restart of production in early May, BW Opal has continued gas production and export activities as part of the project's commissioning and ramp-up program.

BW Offshore said production is being managed in close coordination with Santos while the remaining commissioning activities are completed.

The BW Opal FPSO is designed to process up to 850 million standard cubic feet of gas per day and produce up to 11,000 barrels per day of stabilized condensate. The vessel will operate at the Barossa gas field, located approximately 285 km offshore Darwin in Australia's Northern Territory.

BW Offshore said it remains focused on safe and stable operations as the project progresses toward Practical Completion, which will conclude the delivery phase and commence the long-term contract period.

Floating Production Week delivers unrivaled overview, insight and analysis to the Offshore Floating Production Systems and Technology market

Floating Liquefaction and Regasification Report And Online Database

  • Annual reports -- Our new 150-page report is the first professional effort to systematically look at the universe of FLNG and FSRU projects in the planning stage – and categorize the likelihood of each making the development investment hurdle.
  • Online database -- The online database is updated every day – with information direct from primary sources. The database is fully searchable. Customized charts and spreadsheets can be directly produced from the database.
  • Customer support -- We are available to assist with technical questions about information in the database and reports -- and assist with any questions about using the database search tools.

Here's what you get!

Request Free Trial